Before any construction can begin, a survey crew carefully surveys and stakes the construction right-of-way to ensure that only the pre-approved construction workspace is cleared.
A large project typically is broken into manageable lengths called “spreads,” and utilizes highly specialized and qualified workgroups.
This crew is responsible for removing trees, boulders and debris from the construction right-of-way and preparing a level-working surface for the heavy construction equipment that follows.

The crew installs silt fence along the edges of streams and wetlands to prevent erosion of disturbed soil. Trees inside the right-of-way are cut down, and the contractor removes or stacks the timber along the side of the right-of-way depending on the landowner’s wishes.
Trenching
The trenching crew typically uses a wheel trencher or backhoe to dig the pipe trench. DOT requires the top of a pipeline to be buried a minimum of 30 inches below the ground surface. The pipeline must be buried even deeper at river and road crossings.
If the crew finds large quantities of solid rock during the trenching operation, it uses special equipment or explosives to remove the rock. The crew uses explosives carefully, in accordance with state and federal guidelines, to ensure a safe and controlled blast.
In cultivated areas, the topsoil over the trench is removed first and kept separate from the excavated subsoil, a process called topsoiling. As backfilling operations begin, the soil is returned to the trench in reverse order with the subsoil put back first, followed by the topsoil. This process ensures the topsoil is returned to its original position.
Other steps in the constructions process:
- Clearing, grading and trenching
- Stringing and welding pipe segments together
- Depositing the pipeline, backfilling and testing
- Restoration
More on this...
-
Movie - Clearing the Right of Way
Last updated: 07/16/2007
An overview of the first stages of constructing an interstate natural gas pipelines is shown in this instructional video.

35MB, MOV